300-plus local data center bans have only delayed just three US projects
More than 300 local data center construction moratoriums haven’t had a massive impact on planned buildouts, with only three projects at about 2.3 out of 21 gigawatts (GW) of data centers in moratorium areas likely to be delayed, with a total of 38 GW projected to come online next year, SemiAnalysis shared on X. Per-project audits of the moratoriums indicate that they tend to miss the site, the permit, or the timeline.
The crux of the report is that, while everyone thinks the moratoriums are killing the U.S. buildout, its forecast has “barely moved over the last 12 months.” This forecast includes 38 GW of U.S. data center IT capacity in 2027, which is more than double that of 2026. Of that, 22 GW is under vertical construction, and the other 16 GW is mostly financed, with site work being done. …